October 5, 2025Journal of Engineering Project and Production Management0 citationsOpen Access

Risk Mitigation Based on ISM-MICMAC Method for Subsidized Housing Development in Construction Stage

View Full Paper
ILI Gusti Agung Ayu Istri LestariDSDewa Ketut SudarsanaIAI Nyoman Yudha Astana

Key Points

  • A total of fifty-five risks were identified during the construction stage, with five categorized as major risks.
  • The study established twelve mitigation strategies based on their estimated impacts to manage these key risks effectively.
  • Using the ISM method and the MICMAC framework, the relationships between mitigation variables were thoroughly analyzed, revealing five hierarchical pathways.
  • The proposed risk mitigation model aims to provide actionable insights for subsidized housing developers to reduce risks during construction.

Abstract

The development of subsidized housing, which includes a construction process, is inseparable from risks that can hinder development and cause losses. Risks need to be managed and followed up properly and in a structured manner. This study presents a risk mitigation hierarchy for the development of subsidized housing during the construction period. The risks mitigated are major risks that have been analyzed in previous studies, specifically during the construction stage. The risk mitigation hierarchy for the construction stage of subsidized housing development was analyzed using the Interpretive Structural Modeling–Cross Impact Matrix Multiplication Applied to Classification (ISM-MICMAC) integration method. Fifty-five risks were identified at the construction stage, and five of them are major. Twelve mitigations are arranged based on the estimated impacts they will cause. The relationship between mitigation variables is analyzed using the ISM method followed by analysis using the MICMAC method. Five levels of hierarchy with a total of fifty- five contextual relationships between variables are spread across three quadrants on the MICMAC diagram: driver/independence linkage, and dependence. No mitigation falls into the autonomous quadrant. Mitigations that falls into the driver/independence category equals six, the linkage quadrant equals two, and the dependence quadrant equals four. Three hierarchical pathways divide the five levels of hierarchy, each with its driver for mitigation. The first path involves selecting competitive suppliers and construction cost efficiency including innovation in materials and technology. The second path is establishing structured communication between project parties. The third path is to maximize the bank credit ceiling. This risk mitigation model is expected to provide input to reduce or eliminate risks for subsidized housing developers during the construction stage.

Ask AI
Helpful
Bookmark
Share
View Full Paper

Cite This Study

Lestari et al. (2025) studied this question.

synapsesocial.com/papers/68e25385d6d66a53c2474d97https://doi.org/10.32738/jeppm-2025-121