The construction of the TITANIUM building was started in 2008 near the main railway station in Brno, along the left side of Nové Sady Street. This was followed by the southern extension and expansion of the IN SADY building, then the northward extension of the TITANIUM X and CENTROPOLIS buildings. Various special foundation methods were used in the construction of the building pits and the actual foundation of the buildings. Responses to the realistic form of neogenic clay were also important.
Petr Svoboda (Fri,) studied this question.