Branch-and-bound methods are commonly used to find a permutation schedule that minimizes maximum completion time in an m-machine flow-shop. In this paper we describe a classification scheme for lower bounds that generates most previously known bounds and leads to a number of promising new ones as well. After a discussion of dominance relations within this scheme and of the implementation of each bound, we report on computational experience that indicates the superiority of one of the new bounds.
Lageweg et al. (Wed,) studied this question.