Why Contracts Fail: Financial Risk Factors in Urban Pedestrian Bridge Construction in Indonesia

View Full Paper
APAgung PutrantoAJArman JayadyHNHari Nugraha Nurjaman

Key Points

  • Regular payments for materials, financial management, and execution funds are high-risk factors in bridges.
  • The analysis identified 24 validated risks from an initial 60 through expert consultations and structured questionnaires.
  • Using the risk management framework of ISO 31000:2018, critical risks were analyzed with tools like Ishikawa diagrams and PIM.
  • Improving financial evaluations and contract clauses can mitigate risks and enhance project success for future constructions.

Abstract

Contract termination in public infrastructure projects reflects a failure not only in performance but also in early risk management. This study investigates the dominant risk factors that led to the contract termination of two pedestrian bridge (JPO) construction projects in Jakarta, Indonesia: the North-East Jakarta bridges. Adopting a qualitative case study approach, the research applies the risk management framework of ISO 31000:2018, integrating Ishikawa diagrams and the Probability Impact Matrix (PIM) to identify, validate, and analyze critical risks. Data were collected through literature review, field interviews, and structured questionnaires with key stakeholders, including project owners, contractors, and consultants. A total of 60 risk variables were initially identified, of which 24 were validated by experts. The PIM analysis revealed that three risk factors—irregular payment for materials, poor financial management, and insufficient execution funds—fell within the high-risk zone. All three were categorized under financial risk, highlighting the central role of financial preparedness in project continuity. These findings are consistent with prior studies emphasizing finance as a recurrent cause of project underperformance. Response strategies were formulated through expert consultation and include strengthening contract clauses related to payment, improving contractors’ financial evaluation during tendering, and deploying financial management systems on-site. The study offers practical recommendations for public agencies and contractors to mitigate financial risks and reduce the likelihood of contract termination in future projects. It also contributes to the growing body of knowledge on risk management in public construction projects in emerging economies

Ask AI
Helpful
Bookmark
Share
View Full Paper

Cite This Study

Putranto et al. (2025) studied this question.

synapsesocial.com/papers/68af4ec6ad7bf08b1ead80abhttps://doi.org/10.47191/etj/v10i08.06
Ask AI
Helpful
Bookmark
Share
View Full Paper

Also Consider

Synapse has enriched 5 closely related papers on similar clinical questions. Consider them for comparative context:

  1. 1Managing Cost and Schedule Risks in High-Rise Building Projects: A Case Study from Jakarta, Indonesia2025 · 1 citations
  2. 2The Influence of Financial Risk Manajement on Construction Company Effectiviness at East Java, Indonesia2026
  3. 3Improving project performance strategy on residential infrastructure based on risk management2025 · 1 citations
  4. 4ASSESSMENT OF SCHEDULE UNCERTAINTY AND RISK MITIGATION IN ACCELERATED BRIDGE CONSTRUCTION USING PERT2025
  5. 5Analyzing Construction Risk Factors in Large-Scale Projects: Case Study on the Suramadu Bridge2024 · 1 citations