Risk Analysis of Construction Delays in High-Rise Projects

View Full Paper
AAA. Syamsinar AsmiMRMuhammad Geri RahmadiADAurino Djamaris

Key Points

  • Key findings indicate that financial instability is a significant cause of construction delays.
  • The analysis identified risk factors impacting projects, including material price fluctuations and labor fatigue.
  • A descriptive qualitative approach was utilized, incorporating interviews and questionnaires among industry professionals.
  • The study emphasizes that improved design coordination and contingency plans can mitigate project delays.

Abstract

Delays in construction projects remain a critical challenge in project management, often resulting in schedule deviations, cost overruns, and reduced project quality. This study investigates the primary risk factors contributing to delays in a high-rise educational building project (XYZ School) in Indonesia. Adopting a descriptive qualitative approach, data were collected through structured interviews and questionnaires with ten experienced construction professionals. The analysis utilized the Fishbone (Ishikawa) diagram to trace causal pathways and a probability–impact matrix to assess the severity and likelihood of each identified risk. Findings reveal that financial instability—particularly due to fluctuations in material prices (e.g., steel rising from IDR 8,800 to IDR 12,000/kg)—and poor cash flow management are the most critical causes of delay. Other significant risks include frequent design revisions, labor fatigue from excessive overtime, and adverse weather conditions. The study concludes with strategic recommendations to mitigate these risks, emphasizing improved financial planning, enhanced design coordination, and proactive contingency scheduling.

Ask AI
Helpful
Bookmark
Share
View Full Paper

Cite This Study

Asmi et al. (2025) studied this question.

synapsesocial.com/papers/68bb42272b87ece8dc958f3ehttps://doi.org/10.47191/ijmra/v8-i08-28
Ask AI
Helpful
Bookmark
Share
View Full Paper

Also Consider

Synapse has enriched 5 closely related papers on similar clinical questions. Consider them for comparative context:

  1. 1Managing Cost and Schedule Risks in High-Rise Building Projects: A Case Study from Jakarta, Indonesia2025 · 1 citations
  2. 2Factors Causing Time Delays Completion of Construction Projects (Case Study on Facilities Building Construction Project Sports Stage 5 Construction of The East Stand)2024
  3. 3Critical Risk Factors influencing Time Schedule of Residential Projects in Pakistan2024 · 4 citations
  4. 4Time Delay Risk Analysis in SMPN 2 Mantup Classroom Construction2025
  5. 5Exploring the impact of critical risk interrelationships on design management outcomes in high-rise residential construction projects2026 · 1 citations