September 10, 2025Journal of architecture and civil engineering.1 citations

Managing Cost and Schedule Risks in High-Rise Building Projects: A Case Study from Jakarta, Indonesia

View Full Paper
ASAlifia Indra SeptiajiAJArman JayadyFSFitri Suryani

Key Points

  • Identified five dominant risk factors that significantly impact cost and schedule in high-rise projects.
  • The study utilized the probability impact matrix to categorize risks, highlighting 32 distinct risk factors.
  • Employing qualitative descriptive methods, expert opinions shaped risk management practices for contractors.
  • Findings emphasize the importance of structured mitigation strategies to enhance efficiency in project delivery.

Abstract

Building construction projects are inherently complex and exposed to various risks that may significantly affect project performance, particularly in terms of cost and time. This study investigates risk management practices from the perspective of the contractor on the XY Building Construction Project in Jakarta, Indonesia. A qualitative descriptive methodology was employed, involving literature review, expert interviews, and structured questionnaires to identify potential risks. Risk analysis was conducted using the Probability Impact Matrix (PIM) method, where 32 risk factors were identified and validated by experienced professionals. From the analysis, five dominant risks were categorized as high-priority, including, target production shortfalls, delays in external approvals, late material deliveries, inefficient management coordination, and limited access for heavy equipment. Appropriate mitigation strategies were formulated based on expert responses, including improved onsite management, vendor diversification, and traffic coordination for equipment access. These strategies aim to minimize the impact of critical risks and enhance project delivery efficiency. The findings contribute to a better understanding of risk prioritization and practical response planning in high-risk building construction environments.

Ask AI
Helpful
Bookmark
Share
View Full Paper

Cite This Study

Septiaji et al. (2025) studied this question.

synapsesocial.com/papers/68c1b82654b1d3bfb60eca91https://doi.org/10.35629/8193-10080109
Ask AI
Helpful
Bookmark
Share
View Full Paper

Also Consider

Synapse has enriched 5 closely related papers on similar clinical questions. Consider them for comparative context:

  1. 1Construction Safety in Girder Installation Work on Cibitung – Cilincing Toll Road Construction Project2024 · 3 citations
  2. 2RISK MANAGEMENT OF TIME CONTROL ON THE CONSTRUCTION OF SAUMLAKI PORT2022 · 3 citations
  3. 3MANAJEMEN RISIKO PADA PROYEK GEDUNG BERTINGKAT DI BANJARMASIN2018 · 7 citations
  4. 4MANAJEMEN RISIKO PADA PELAKSANAAN PROYEK KONSTRUKSI GEDUNG PEMERINTAH DI KOTA DILI – TIMOR LESTE1970 · 8 citations
  5. 5MANAJEMEN RISIKO PADA PROYEK PEMBANGUNAN GEDUNG ASRAMA MAHASISWA UIN WALISONGO TAHUN 20212021 · 9 citations