September 16, 2025Buildings2 citationsOpen Access

Research on Construction Period Optimization of High-Rise Buildings Based on Integrated Building Platform Applications

View Full Paper
SWShuqiang WangCHChenxi HuQWQingqing Wu

Key Points

  • The optimization model reduced standard-floor construction time from 6 to 4 days, achieving a 33.3% efficiency gain.
  • It also decreased idle time by 41% through improved resource allocation and process management.
  • The study utilizes genetic algorithms and integrated building platforms to develop a novel optimization approach.
  • This approach enhances construction efficiency, providing both theoretical and practical solutions for the building industry.

Abstract

This study optimizes high-rise residential construction schedules using Integrated Building Platforms and genetic algorithms. By analyzing process sequences and overlapping relationships, a schedule optimization model is developed to overcome inefficiencies in traditional sequential methods. The model leverages multi-layer collaboration, enabling parallel and interwoven processes while considering overlapping logic and time constraints. Validated with a real case, the model reduced standard-floor construction from 6 to 4 days (33.3% efficiency gain) and cut idle time by 41%. The approach breaks traditional limitations, maximizing platform advantages for improved resource allocation and process management. The research offers a scientific, efficient scheduling solution for high-rise construction, demonstrating significant theoretical and practical value. It presents a novel optimization method for the building industry.

Ask AI
Helpful
Bookmark
Share
View Full Paper

Cite This Study

Wang et al. (2025) studied this question.

synapsesocial.com/papers/68d453a431b076d99fa59a3chttps://doi.org/10.3390/buildings15183338