Risk Management in Implementation City Road Project in Padang City

View Full Paper
RPRifano PutraTOTaufika OphiyandriBHBenny Hidayat

Key Points

Key points are not available for this paper at this time.

Abstract

Risks can have an impact on the productivity, performance, quality and cost limits of a project and risks can be said to be consequences that may occur unexpectedly. The success of a construction project really depends on the ability of project management to manage the risks that occur. The role of transportation in the city of Padang is to support the economic, education, tourism and defense and security sectors. Construction projects are a dynamic field and contain risks. The aim of this research is to identify risks and carry out risk analysis in the implementation of city road construction projects in the city of Padang as well as carry out risk responses for risk ownership in order to reduce the consequences caused by these risks. This research uses primary and secondary data which will later become a questionnaire and conduct interviews. Questionnaires were distributed to respondents, namely contractors, the results of the questionnaire calculation analysis using the Severity Index (SI) method from during the implementation of urban road construction in the city of Padang, 47 (forty seven) risks were identified based on activities at the project implementation stage. The risks identified are 2 (two) political risks, 7 (seven) environmental risks, 2 (two) planning risks, 2 (two) marketing risks, 3 (three) economic risks, 1 (one) financial risk, 6 ( six) natural risks, 7 (seven) project risks, 7 (seven) technical risks, 2 (two) human risks, 3 (three) criminal risks and 5 (five) safety risks. Of the identified risks, an analysis of the level of risk acceptance was carried out which showed that there were 23 (twenty-three) risks that were included in the highest risk category or unacceptable risk category (Unacceptable) and 24 (twenty-four) risks that were included in the risk category. not expected (Undesirable). Ownership of the greatest risks is the responsibility of the contractor because during the project, the contractor has a central role as controlling the overall course of the project.

Ask AI
Helpful
Bookmark
Share
View Full Paper

Cite This Study

Putra et al. (2024) studied this question.

synapsesocial.com/papers/68e62882b6db6435875bb127https://doi.org/10.24036/cived.v11i2.570
Ask AI
Helpful
Bookmark
Share
View Full Paper

Also Consider

Synapse has enriched 5 closely related papers on similar clinical questions. Consider them for comparative context:

  1. 1Analisis Tingkat Risiko Proyek Pelaksanaan Pemeliharaan Jalan Untuk Meningkatkan Kinerja Mutu Proyek Jalan Di Kabupaten Malang2017 · 5 citations
  2. 2Manajemen Risiko Proyek Konstruksi Jalan (Studi Kasus: Preservasi Rekonstruksi Jalan Lambaro – Bts. Pidie)2021 · 3 citations
  3. 3ANALISIS RISIKO DALAM PROYEK JALAN RAYA DI KABUPATEN MALANG2017 · 2 citations
  4. 4FAKTOR PENYEBAB KERUSAKAN LINGKUNGAN SEKITAR AKIBAT PEMBANGUNAN UNDERPASS STUDI KASUS : UNDERPASS MAKAMHAJI, SUKOHARJO2018 · 2 citations
  5. 5ANALISIS RISIKO PADA TAHAP PELAKSANAAN KONSTRUKSI JALAN TOL CINERE – JAGORAWI, DEPOK2021 · 4 citations