Key Factors and Transmission Mechanisms ofCost Risk in General Engineering ContractingProjects Based on Legal Cases

View Full Paper
XWXumin WangKKKang Kai

Key Points

  • This research aims to identify and categorize cost risk factors in EPC projects through judicial case analysis.
  • Analyzed 212 judicial cases from the China Judgments Online database.
  • Employed social network analysis (SNA) to identify relationships among risk factors.
  • Applied the Apriori algorithm to uncover co-occurrence patterns of risks.
  • Identified 24 cost risk factors forming a multilevel risk structure.
  • Found that legal, technical, and managerial risks are key contributors to cost overruns.
  • Demonstrated strong applicability of the data-driven framework in different legal contexts.

Abstract

The engineering–procurement–construction (EPC) model has been widely adopted in construction practice for its ability to achieve efficient integration and unified coordination across project phases. However, the diversity and complexity of cost risk factors in EPC projects pose significant challenges to effective cost control. This study systematically analyzes 212 judicial cases from the China Judgments Online database to extract and categorize 24 cost risk factors, forming a multilevel risk structure. Social network analysis (SNA) is employed to identify the structural relationships among these risk factors, while the Apriori algorithm is applied to uncover frequent cooccurrence patterns, revealing the coupling mechanisms and transmission pathways of core risks. The results indicate that a system science–based classification approach effectively supports the identification and modeling of complex risk networks. Legal, technical, and managerial risks emerge as key nodes contributing to cost overruns, with strong coupling and bidirectional feedback observed among multiple factors. Furthermore, the proposed data-driven analytical framework demonstrates strong cross-jurisdictional applicability, providing theoretical and methodological guidance for project risk governance under different legal and regulatory contexts. This research deepens the theoretical understanding of systemic cost risk behaviors in EPC projects and offers empirical and practical insights for improving contract governance and risk control in international EPC practices.

Ask AI
Helpful
Bookmark
Share
View Full Paper

Cite This Study

Wang et al. (2026) studied this question.

synapsesocial.com/papers/6a153a2eb5d9c58d83e8d022https://doi.org/10.1061/jladah.ladr-1463
Ask AI
Helpful
Bookmark
Share
View Full Paper