April 1, 2002Journal of Computing in Civil Engineering193 citations

Formalization and Automation of Time-Space Conflict Analysis

View Full Paper
BABurcu AkinciMFMartin FischenRLRaymond E. Levitt

Key Points

Key points are not available for this paper at this time.

Abstract

With increasing pressure for shorter delivery schedules, space is a critical resource at construction sites. Current industry practice lacks a formalized approach or tool to help project managers analyze spatial conflicts between activities prior to construction. Consequently, time-space conflicts occur frequently and significantly impact construction processes. Time-space conflicts have three characteristics that impede the detection and analysis of time-space conflicts prior to construction: (1) They have a temporal aspect; (2) they have different forms creating different problems; and (3) multiple types of spatial conflicts can exist between a pair of conflicting activities. This research formalizes time-space conflict analysis as a classification task and addresses these challenges by automatically (1) detecting conflicts in four dimensions; (2) categorizing the conflicts according to a taxonomy of time-space conflicts that is developed; and (3) prioritizing the multiple types of conflicts between the same pair of conflicting activities. This research extends previous research on construction space management by developing a taxonomy of time-space conflicts and by defining an approach for the analysis of time-space conflicts prior to construction.

Ask AI
Helpful
Bookmark
Share
View Full Paper

Cite This Study

Akinci et al. (2002) studied this question.

synapsesocial.com/papers/6a1e76bf25b49a996c68e85ehttps://doi.org/10.1061/(asce)0887-3801(2002)16:2(124)
Ask AI
Helpful
Bookmark
Share
View Full Paper

Also Consider

Synapse has enriched 5 closely related papers on similar clinical questions. Consider them for comparative context:

  1. 1Modeling Work Space to Schedule Repetitive Floors in Multistory Buildings1994 · 116 citations
  2. 2Time-Space Conflict Analysis Based on 4-D Production Models1998 · 22 citations
  3. 3Productivity improvement in construction1988 · 514 citations
  4. 4Factors affecting project success in the piping function2010 · 32 citations
  5. 5Exchanging layout and schedule data in a real-time distributed environment1993 · 11 citations