Probabilistic Cost Estimating with Subjective Correlations

View Full Paper
ATAli Touran

Key Points

Key points are not available for this paper at this time.

Abstract

One of the difficulties in probabilistic estimating is accounting for the existing correlations among cost components modeled as random variables. Even if the estimator is aware of the existence of correlations among random variables, calculating accurate values of correlation coefficients is not feasible most of the time. A methodology for generating correlated random numbers in a Monte Carlo simulation for construction cost estimating is reviewed. A methodology is then suggested that simplifies the process of incorporating the effect of correlation coefficients in probabilistic estimating. This methodology consists of assigning subjective measures of correlation between variables. Also, a method is suggested for adjusting the covariance matrix in which correlation estimates are not accurate. Procedures presented are further explained by two examples using actual construction cost data.

Ask AI
Helpful
Bookmark
Share
View Full Paper

Cite This Study

Ali Touran (1993) studied this question.

synapsesocial.com/papers/6a20b9349f43da0f9dab34fehttps://doi.org/10.1061/(asce)0733-9364(1993)119:1(58)
Ask AI
Helpful
Bookmark
Share
View Full Paper

Also Consider

Synapse has enriched 5 closely related papers on similar clinical questions. Consider them for comparative context:

  1. 1Monte Carlo Technique with Correlated Random Variables1992 · 146 citations
  2. 2Probability and Statistics for Engineering and the Sciences.1991 · 2,521 citations
  3. 3Introduction to simulation and SLAM II1979 · 1,246 citations
  4. 4Uncertainty1990 · 1,703 citations
  5. 5A distribution-free approach to inducing rank correlation among input variables1982 · 1,622 citations