On Scheduling with Ready Times and Due Dates to Minimize Maximum Lateness

View Full Paper
GMGraham McMahonMFMichaël Florian

Key Points

Key points are not available for this paper at this time.

Abstract

An algorithm is developed for sequencing jobs on a single processor in order to minimize maximum lateness, subject to ready times and due dates. The method that we develop could be classified as branch-and-bound. However, it has the unusual feature that a complete solution is associated with each node of the enumeration tree.