October 28, 2019Journal of Construction Engineering and Management326 citations

Machine Learning Algorithms for Construction Projects Delay Risk Prediction

View Full Paper
AGAhmed GondiaASAhmad SiamWEWael El‐Dakhakhni

Key Points

Key points are not available for this paper at this time.

Abstract

Projects delays are among the most pressing challenges faced by the construction sector attributed to the sector’s complexity and its inherent delay risk sources’ interdependence. Machine learning offers an ideal set of techniques capable of tackling such complex systems; however, adopting such techniques within the construction sector remains at an early stage. The goal of this study was to identify and develop machine learning models in order to facilitate accurate project delay risk analysis and prediction using objective data sources. As such, relevant delay risk sources and factors were first identified, and a multivariate data set of previous projects’ time performance and delay-inducing risk sources was then compiled. Subsequently, the complexity and interdependence of the system was uncovered through an exploratory data analysis. Accordingly, two suitable machine learning models, utilizing decision tree and naïve Bayesian classification algorithms, were identified and trained using the data set for predicting project delay extents. Finally, the predictive performances of both models were evaluated through cross validation tests, and the models were further compared using machine-learning-relevant performance indices. The evaluation results indicated that the naïve Bayesian model provides a better predictive performance for the data set examined. Ultimately, the work presented herein harnesses the power of machine learning to facilitate evidence-based decision making, while inherent risk factors are active, interdependent, and dynamic, thus empowering proactive project risk management strategies.

Ask AI
Helpful
Bookmark
Share
View Full Paper

Cite This Study

Gondia et al. (2019) studied this question.

synapsesocial.com/papers/6a5bc3b9c79753f37d04c22bhttps://doi.org/10.1061/(asce)co.1943-7862.0001736
Ask AI
Helpful
Bookmark
Share
View Full Paper

Also Consider

Synapse has enriched 5 closely related papers on similar clinical questions. Consider them for comparative context:

  1. 1Bayesian Decision Tool for the Analysis of Occupational Accidents in the Construction of Embankments2016 · 44 citations
  2. 2Notice of Retraction: Review of decision trees2010 · 34 citations
  3. 3Classifying Construction Contractors Using Unsupervised-Learning Neural Networks2006 · 31 citations
  4. 4Applying Artificial Neural Networks for Measuring and Predicting Construction-Labor Productivity2015 · 162 citations
  5. 5Data mining in mining engineering: results of classification and clustering of shovels failures data2016 · 35 citations