Fluid handling and civil structure of a minihydroelectric power plant project in an irrigation district in Colombia

View Full Paper
FCFreddy Sotto CaperaCSCamila Cerquera SandovalJVJean Carlos Acosta Vargas

Key Points

  • The aim is to design a mini-hydroelectric power plant to supply electricity in a rural area using local resources.
  • Designed hydraulic and structural components for a minihydroelectric power plant.
  • Utilized suitable flow rates and head conditions for a Michell-Banki turbine.
  • Constructed civil infrastructure to maintain pressure and convey water efficiently.
  • Developed a reinforced frame to support turbine and generator under various loads.
  • Achieved a flow rate of 0.24 m3/s for generating approximately 20 kW of electrical power.
  • Utilized low-cost local manufacturing methods for turbine construction.
  • Provided a replicable model for similar rural electrification projects.

Abstract

Abstract This study presents the hydraulic and structural design of a mini-hydroelectric power plant implemented in the USOIGUA irrigation district, located in the municipalities of Campoalegre and Hobo (Huila, Colombia). The system was conceived to supply electricity to a household in a non-interconnected rural zone, leveraging an available flow rate between 0.87 and 1.24 m3/s and a net head of 18 m. These conditions were found suitable for a Michell-Banki turbine, which was built using low-cost, locally available manufacturing methods. To ensure proper turbine operation, the project required the design and construction of a civil infrastructure capable of conveying water from an upstream intake while maintaining pressure at the injector. A reinforced structural frame was also developed to support the turbine, transmission, and generator, designed to resist both static and dynamic loads and to provide environmental protection. The resulting system was dimensioned for a flow rate of 0.24 m3/s, aiming to generate approximately 20 kW of electrical power. The project demonstrates the integration of accessible construction practices with renewable energy technologies and offers a replicable model for rural electrification in similar geographic contexts.

Ask AI
Helpful
Bookmark
Share
View Full Paper

Cite This Study

Capera et al. (2026) studied this question.

synapsesocial.com/papers/6969d428940543b977708ff8https://doi.org/10.1590/0370-44672025790042
Ask AI
Helpful
Bookmark
Share
View Full Paper