Scenario Planning for a Sustainable Reduction in Construction Delay and Disruption Disputes

View Full Paper
VAVasil Angelov Atanasov

Key Points

  • Evaluate how scenario planning can provide solutions to mitigate delays in the construction sector caused by climate change.
  • Literature analysis and synthesis
  • Evaluation of results from a scenario-planning workshop
  • Identification of key forces impacting construction by 2030
  • Identified climate change and profit margins as major influences on construction by 2030.
  • Proposed the Trilateral Model for effective risk allocation in contracts.
  • Highlighted the need for modifying contract terms to address climate-related risks.

Abstract

Although the expected future impacts of climate change on the construction sector are significant and commonly accepted, the prospect and viability of contractual solutions to mitigate such effects lack investigation. Scenario planning enables leaders to prepare for the future by revealing the impending opportunities and threats to businesses and markets. This article offers analysis, synthesis, and evaluation of published literature and results from a scenario-planning workshop. The study reveals that climate change and profit margins are the main forces that will impact the construction sector in 2030. Evidential materials, contract provisions, and data repositories involving existing and emerging technologies are the three tenets of an innovative conceptual solution that can reduce delay and disruption disputes. This is significant because, inter alia, as the consequences of climate change are likely to increase, contract terms that allocate risks associated with it are likely to be modified, and insurance companies are liable to increase indemnification premiums, or become unable to cover such risks. The offered solution, namely the Trilateral Model, increases the sustainability of construction contracting in this context through a clear, impartial, acceptable, and effective risk allocation mechanism that mitigates the impact of those forces and offers contractual certainty.

Ask AI
Helpful
Bookmark
Share
View Full Paper

Cite This Study

Vasil Angelov Atanasov (2026) studied this question.

synapsesocial.com/papers/69aa7037531e4c4a9ff59d11https://doi.org/10.3390/buildings16051007
Ask AI
Helpful
Bookmark
Share
View Full Paper