When the cost of reducing the duration of activities is convex and nonlinear, it may be advisable (to reduce the computing burden) to seek a “satisficing” answer, in which the project is compressed to a desired completion time with a prespecified tolerable relative error. We treat the problem of constructing the optimal first degree interpolating linear spline that guarantees such maximal error and consider various possible refinements.
No takes yet. Share an insight, caveat, or question.
Adel et al. (1984) studied this question.