A modified shifting bottleneck heuristic for minimizing total weighted tardiness in complex job shops

View Full Paper
SMScott J. MasonJFJohn FowlerWCW. Matthew Carlyle

Key Points

Key points are not available for this paper at this time.

Abstract

Increases in the demand for integrated circuits have highlighted the importance of meeting customer quality and on-time delivery expectations in the semiconductor industry. A modified shifting bottleneck heuristic is developed for minimizing the total weighted tardiness in a semiconductor wafer fabrication facility. This 'complex' job shop is characterized by re-entrant or re-circulating product flow through a number of different tool groups (one or more machines operating in parallel). These tool groups typically contain batching machines, as well as machines that are subject to sequence-dependent setups. The disjunctive graph of the complex job shop is presented, along with a description of the proposed heuristic. Preliminary results indicate the heuristic's potential for promoting on-time deliveries by semiconductor manufacturers for their customers' orders. Copyright © 2002 John Wiley & Sons, Ltd.

Ask AI
Helpful
Bookmark
Share
View Full Paper

Cite This Study

Mason et al. (2002) studied this question.

synapsesocial.com/papers/6a1efdd095bd0d03bde6b543https://doi.org/10.1002/jos.102
Ask AI
Helpful
Bookmark
Share
View Full Paper

Also Consider

Synapse has enriched 5 closely related papers on similar clinical questions. Consider them for comparative context:

  1. 1Machine Sequencing Via Disjunctive Graphs: An Implicit Enumeration Algorithm1969 · 403 citations
  2. 2Decomposition Methods for Complex Factory Scheduling Problems1997 · 220 citations
  3. 3Scheduling: Theory, Algorithms, and Systems1996 · 6,288 citations
  4. 4A heuristic to minimize the total weighted tardiness with sequence-dependent setups1997 · 281 citations
  5. 5Rolling horizon procedures for dynamic parallel machine scheduling with sequence-dependent setup times1995 · 150 citations