Qatari construction projects frequently encounter significant delays. One of the major causes of these delays is ignoring Qatar's extreme weather conditions on labour productivity. This paper studies the impact of temperature, humidity, and wind on labour productivity in Qatar for four construction trades, namely, formwork, masonry, plaster, and ceramic tiles. These trades were chosen because they are time-consuming and commonly found in most construction projects. Weather and trade labour productivity data were recorded between July 2013 and February 2014. The results showed that weather conditions have a high impact on trade labour productivity. They also showed that the labour productivity in the summer can be as low as half of that in the winter. Linear regression models were developed to predict trade productivity on a given day of the year.