April 1, 2002Operations Research200 citations

Short-Term Generation Asset Valuation: A Real Options Approach

View Full Paper
CTChung‐Li TsengGBGraydon Barz

Key Points

Key points are not available for this paper at this time.

Abstract

This paper discusses using real options to value power plants with unit commitment constraints over a short-term period. We formulate the problem as a multistage stochastic problem and propose a solution procedure that integrates forward-moving Monte Carlo simulation with backward-moving dynamic programming. We assume that the power plant operator maximizes expected profit by deciding in each hour whether or not to run the unit, that a certain lead time for commitment and decommitment decisions is necessary to start up and shut down a unit, and that these commitment decisions, once made, are subject to physical constraints such as minimum uptime and downtime. We also account for the costs associated with starting up and shutting down a unit. Last, we assume that there are hourly markets for both electricity and the fuel used by the generator and that their prices follow Ito processes. Using numerical simulation, we show that failure to consider physical constraints may significantly overvalue a power plant.

Ask AI
Helpful
Bookmark
Share
View Full Paper

Cite This Study

Tseng et al. (2002) studied this question.