We consider the scheduling of n jobs on m identical machines when the jobs become available for processing at ready times a i , a i , ⩾ 0, require d i time units for processing and must be completed by times b i for i = 1, 2, … n . The objective chosen is that of minimizing the total elapsed time to complete all jobs subject to the ready time and due date constraints, preemption is not allowed. We present a multi‐stage solution algorithm for this problem that is based on an implicit enumeration procedure and also uses the labelling type algorithm which solves the problem when preemption is allowed.
No takes yet. Share an insight, caveat, or question.
Bratley et al. (1975) studied this question.