Transmission switching (TS) is introduced to add flexibility to the transmission and generation capacity expansion planning problem. TS could improve the performance of the capacity expansion planning model and reduce the total planning cost. The capacity expansion planning problem is decomposed into a master problem and two subproblems. The master problem utilizes the candidate set for additional generating unit and transmission capacity investments to find the optimal plan throughout the planning horizon. The subproblems use the optimal plan, apply transmission switching to relieve any transmission flow violations, and calculate the optimal dispatch of generating units. The transmission network contingencies are also considered in the subproblems. The case studies exhibit the effectiveness of the proposed expansion planning approach.