Summary The Long Beach Oil Development Co. (LBOD) tertiary immiscible CO2 project began in March 1982 with the injection of a mixture of about 85% CO2/15% N2 into the Tar zone of Fault Block V in the Wilmington field, Los Angeles County, CA. The 330-acre [134-ha] project had been waterflooded since 1961, and the water cut was more than 95%. Gas was injected alternately with water for a period of about 5 years. This paper reviews project performance from inception to the end of 1987.