A simple dynamic model is developed that describes some of the important aspects of research and development projects. Its purpose is illustration of the applicability of dynamic modelling to understanding the key factors affecting R & D performance. The model recognizes the differences among real, perceived, and reported progress on the job. It also includes the effect of schedule pressures on productivity. Simulation results are presented that, among other things, illustrate the trade‐off between meeting schedule and maintaining organizational stability, the effects of rapid problem detection and response, and the difficulties due to the intangible nature of R & D progress.