The sequencing batch reactor (SBR) was used for in situ studies of piggery wastewater treatment. The SBR was a concrete basin 5 mL × 2.5 mW × 4 mH. The study was performed on a selected pig farm in Taiwan. The working volume was 37.5 m3 and hydraulic retention time (HRT) was 3 days with the BOD volumetric loading of 0.357 kg‐BOD/m3/day. The removal rates of BOD, COD, and SS were 94.5, 88.7, and 93.4%, respectively. However, the removal rates of nitrogen (NH4 +‐N, NO3 −‐N, and TKN) and phosphorus were 36.3–52.9 and 61.1%, respectively. The results imply the feasibility of extending SBR system to pig fanners for piggery wastewater treatment in Taiwan.
No takes yet. Share an insight, caveat, or question.
Su et al. (1997) studied this question.