This paper considers a single machine scheduling problem in which each job is assigned an individual due date based on a common flow allowance (i.e. all jobs have slack due date). The goal is to find a sequence for jobs, together with a due date assignment, that minimizes a non-regular criterion comprising the total weighted absolute lateness value and common flow allowance cost, where the weight is a position-dependent weight. In order to solve this problem, an time algorithm is proposed. Some extensions of the problem are also shown.
No takes yet. Share an insight, caveat, or question.
Liu et al. (2016) studied this question.