“Analysis The Productivity Of Heavy Equipment Cut And Fill Work” (Case Study: Package 6th Leuwikeris Dam Project Tasikmalaya-Banjar)

View Full Paper
YYYanto YantoCFCornelia Gina FransiscaMPMuhamad Decky Pambudi

Key Points

  • Productivity was significantly hindered by factors like equipment breakdowns and weather conditions, limiting project efficiency.
  • The time study clearly showed that delays in material supply also impacted the overall productivity of heavy equipment.
  • Using a range of heavy equipment including excavators and bulldozers, the analysis provided key insights into operational challenges.
  • These findings may enable better civil engineering practices in future dam construction and similar development projects.

Abstract

This research examines the productivity of heavy equipment used in the Cut and Fill work at the Leuwikeris Dam Project in Tasikmalaya, Indonesia. The study highlights the importance of efficient resource utilization and the environmental and social impacts associated with dam construction. A time study method was employed to analyze productivity, focusing on various heavy equipment such as excavators, dump trucks, bulldozers, and vibratory rollers. The findings indicate that factors such as equipment breakdowns, weather conditions, and material supply delays significantly impact productivity. The results aim to inform civil engineering practices and improve the understanding of heavy construction equipment efficiency in development projects.

Ask AI
Helpful
Bookmark
Share
View Full Paper

Cite This Study

Yanto et al. (2025) studied this question.

synapsesocial.com/papers/68af509bad7bf08b1ead85aahttps://doi.org/10.58631/injurity.v4i8.1462