Answers are grounded in this paper and cite their sources.
Quantitative analysis shows a significant impact of interruption time on power output in micro hydropower plants, suggesting improved management strategies.
This study quantitatively investigated the relationship between the output power (kW) of the Bungin Micro Hydropower Plant (MHP) and two independent variables, operating time (hours) and interruption time (hours), using multiple linear regression. The analysis aimed to identify dominant factors influencing energy production efficiency. The resulting regression model, expressed as: Power (kW) = 3656.1 − 1.52 (Operating Time) − 1.02 (Interruption Time), indicates a negative correlation between both operating and interruption times and power output. However, statistical significance testing (p = 0.01) revealed that only interruption time had a significant impact on Bungin MHP's output power. This finding aligns with theoretical expectations that increased interruption durations impede energy generation. While operating time also exhibited a negative coefficient, its effect was not statistically significant (p > 0.05) within this model. Thus, interruption time is identified as the primary determinant of Bungin MHP's energy production, underscoring the critical need for effective interruption management to optimize plant performance.
No takes yet. Share an insight, caveat, or question.
Rahmah et al. (2025) studied this question.
Synapse has enriched 10 related papers. Consider them for comparative context: