Analysis of value engineering demonstrated significant cost savings in construction project, indicating efficient solutions.
Construction project efficiency is the key to success amid budget pressures and cost inflation. Value Engineering (VE) is a systematic solution to balance cost, reliability, and project performance. Pareto analysis identified four main works for optimization: walls, frames, floors, and ceilings with cost/worth ratio >1. Alternative solutions included AAC/HEBEL walls, PVC sills, unpolished homogenius tile, and PVC ceiling. The implementation of Value Engineering resulted in significant savings in walls (38.63%), frames (24.21%), ceilings (46.62%), and floors (39.74%). The total savings reached Rp1.481.761.485,10 (38,52% of the initial cost), with Life Cycle Cost as the main consideration.