Answers are grounded in this paper and cite their sources.
This study explores the integration of fossil and renewable energy generators on Selayar Island, focusing on optimizing Diesel Power Plants (PLTD) and Solar Power Plants (PLTS). Using Mixed-Integer Linear Programming (MILP) for generator scheduling, simulations reveal that a 15% rotational backup constraint positively impacts operational costs and system reliability. The findings provide practical recommendations for operators to enhance efficiency, reduce costs, and improve overall system reliability in the context of hybrid energy systems.
No takes yet. Share an insight, caveat, or question.
Wicaksono et al. (2024) studied this question.
Synapse has enriched 10 related papers. Consider them for comparative context: