Answers are grounded in this paper and cite their sources.
Analysis of sensor data evaluates loads and displacements in the bridge, indicating performance over nearly 5 years.
The bridge over the River Barrow in New Ross, Ireland, opened to traffic in January 2020. The structure has a total length of 887m covered in 9 spans, the two main ones have a span of 230 m, and are supported by three towers and an extrados stay arrangement in a single central plane of the deck that supports a carriageway with two lanes on each direction. The bridge had structural sensors installed that provide information on loads and displacements at all supports, cable loads on at least two stays per tower, as well as extensometers at the four corners of the box in five different sections. Additionally, the bridge has thermal sensors and anemometers. This article presents some initial conclusions resulting from the analysis of the sensor data after nearly 5 years from opening the road to live traffic and their comparison with the structural models considered in the original design and proposes future research themes.
No takes yet. Share an insight, caveat, or question.
Suárez et al. (2025) studied this question.
Synapse has enriched 10 related papers. Consider them for comparative context: