Survey and Alignment of the KLOE Experiment at DAFNE
Key Points
The aim is to detail the survey and alignment efforts for the KLOE experiment at DAFNE.
Reviewed the survey techniques used during the construction phase
Examined the alignment protocols employed for installation
Documented timelines from September 1995 to October 1997
Provided a comprehensive overview of alignment and survey activities
Outlined successful practices for experimental setups in high-energy physics
Abstract
This review describes the survey and alignment program completed for the construction and the installation of the KLOE experiment from September 1995 to October 1997.