The structure of an R & D project is described in terms of an Effort-Distribution Array. A logistic model is presented for the cumulative times series of effort devoted to a project, and problems of using such curves for prediction are discussed. A set of rules is given, which, with the aid of computer simulation, can be used to generate a project schedule. The consequences of several combinations of rules and restrictions are examined.