This paper addresses the bidding problem faced by a virtual power plant (VPP) in a joint market of energy and spinning reserve service. The proposed bidding strategy is a non-equilibrium model based on the deterministic price-based unit commitment (PBUC) which takes the supply-demand balancing constraint and security constraints of VPP itself into account. The presented model creates a single operating profile from a composite of the parameters characterizing each distributed energy resources (DER), which is a component of VPP, and incorporates network constraints into its description of the capabilities of the portfolio. The presented model is a nonlinear mixed-integer programming with inter-temporal constraints and solved by genetic algorithm (GA).
No takes yet. Share an insight, caveat, or question.
Mashhour et al. (2010) studied this question.