A smart distribution system should restore service to interrupted customers as quickly as possible after an outage. Upgrading manual switches to remote-controlled switches (RCSs) enhances restoration capability. The placement of RCSs should consider both functional and economic requirements. This paper presents a systematic method to determine the set of switches to be upgraded for an existing distribution system. The maximum restoration capability is achieved by upgrading a near-minimum number of manual switches to RCSs. The RCS placement problem is formulated as a weighed set cover (WSC) problem. A greedy algorithm with a polynomial-time computational efficiency is designed to generate a near-optimal solution for the WSC problem. A 3-feeder 9-node test system and a 4-feeder 1069-node unbalanced test system with microgrids are used to validate the effectiveness of the proposed method.
Xu et al. (Fri,) studied this question.