In this article we propose a new heuristic solution technique for resource-constrained project scheduling problems. Basically, it is a hybrid of priority rule and random search techniques which employs two types of adaptations in order to determine the solution space. We enhance this general scheme by the use of a new priority rule and by lower bounding techniques. The method is evaluated by comparing it with other recently proposed heuristics on a widely used set of benchmark-instances. Furthermore, we show that the procedure can be usefully applied to solve different hard problems within the field of project scheduling.
No takes yet. Share an insight, caveat, or question.
Kolisch et al. (1996) studied this question.