This is the authors' abstract. We don't add key points for this paper.
A method for quantifying and measuring the effectiveness of contractors competing for a cost-plus contract has been developed. The methodology is demonstrated within the context of a $40,000,000 cost-plus incentive fee contract for electrical work on a nuclear power station. Four candidate contractors are evaluated and ranked using a multicriterion decision model. Comparisons are made between the decision model rankings and those arrived at by more traditional means. The procedure demonstrates the viability of a quantitative approach to a heretofore qualitative problem. Although not accomplished here, the procedure may be adapted to the selection of fixed price contractors as well.
Answers are grounded in this paper and cite their sources.
No takes yet. Share an insight, caveat, or question.
James E. Diekmann (1981) studied this question.
Synapse has enriched 10 related papers. Consider them for comparative context: