SEAM Phase I RPSEA is progressing on schedule toward a completion date of the end of June 2013. Several activities are ongoing as multiple data sets are simulated, compiled, or contracted for simulation. This report is an update on the status of the simulations being conducted on the SEAM Phase I Deepwater Model. A complete listing of the parameters for all simulations on the SEAM Phase I Deepwater model was given in the May 2012 issue of The Leading Edge. Funding for the expanded simulations is provided by the Research Partnership to Secure Energy for America (RPSEA subcontract No. 07121–2001).