It is known that following disturbances, on-load tap changers act to restore the load bus voltage and thus restore the load power to near pre-disturbance level. As the system is probably weakened by the contingencies, this will often over-tax existing supplies due to increased losses and reduction in power plant ability, and thus voltage collapse may result. This paper discusses the less emphasized effect of on-load tap changers from another point of view, i.e., how the maximum power transfer limit is affected by on-load tap changers. In addition to restoring the load, on-load tap changers also extend the power transfer ability. Whether the overall effect is beneficial or counter-productive depends on the system ability to balance the amount of extended power transfer limit and the amount of restored load by the same tap changers.
No takes yet. Share an insight, caveat, or question.
Zhu et al. (2000) studied this question.