Case report reveals poor tool adoption compromises compliance oversight among volunteer teams, highlighting the limits of standard planning without stakeholder engagement.
When Adaeze Okon was unexpectedly handed leadership of an IGNITEx event in Lagos, Nigeria, with fewer than 3 months to the event date, her first instinct was to build a plan. Within days she had created a comprehensive project tracker: colour-coded, role-assigned, deadline-stamped, and shared with the entire volunteer team. It was, by any project management standard, exactly what should be done. The problem was that nobody read it. Weeks later, a compliance gap the tracker should have caught nearly cost the event its licence. Adaeze was left working out, in real time, what a plan is worth when the people it depends on are not using it.