Answers are grounded in this paper and cite their sources.
As a measure of variation, total absolute deviation of job completion times (TADC) has received relatively little attention in scheduling literature. Minimizing TADC on a single machine was shown to have a polynomial time solution. In this note, we extend TADC in two directions: (i) we allow position-dependent processing times and (ii) we consider parallel identical machines. We show that each of these two more general problems, and TADC with both extensions remain polynomially solvable.
No takes yet. Share an insight, caveat, or question.
Gur Mosheiov (2007) studied this question.