This paper presents a hierarchical framework and integer programming formulations for multi-objective production scheduling in a make-to-order manufacturing environment. Integer programming formulations are proposed for the long-term assignment of customer orders to planning periods and the short-term machine assignment and scheduling of production lots in a hybrid flow shop with multi-capacity machines and due-date-related performance measures. The integer programs have been enhanced by the addition of cutting constraints derived for both the long-term customer order assignment and the short-term machine scheduling. Numerical examples modelled on a real-world make-to-order assembly system in the electronics industry are provided and computational results are reported.