Observational analysis shows alloy piping productivity of 10.66 dia inch/day, indicating potential for improvement.
Productivity in construction work is one of the important factors to be able to manage the expenses of a project. One way to find out work productivity is by conducting simulations. This study specifically conducted a study related to the productivity of alloy piping work in the Muara Tawar PLTGU project. Considering that this work requires a lot of resources, and is on a critical track of project completion schedule. Based on CYCLONE modeling and the results of EZSTROBE software simulation, a productivity of 10.66 diainch/day per team was obtained. However, these results can still be optimized up to 15.99 Dia inch/day per team by adding resources to the fitup job.
No takes yet. Share an insight, caveat, or question.
Rendy Yoel (2025) studied this question.
Synapse has enriched 5 closely related papers on similar clinical questions. Consider them for comparative context: