CMTS1 (cryomodule test stand 1) at Fermilab was built to test cryomodules built for the LCLS-II beamline at SLAC and is currently testing cryomodules for LCLS-II-HE, the high energy upgrade to LCLS-II. The first cryomodule test was in 2016 and to date over 30 cryomodules have been tested here. This talk will highlight operational experience of the vacuum systems including insulating, coupler, and a low particulate beamline vacuum system. It will focus on the problems that have come up over the years, their solutions, and mitigations put in place to prevent further issues.