In this paper, we consider two single-machine scheduling problems with deteriorating jobs and controllable processing time. The job processing time is a function of its starting time and resource allocation. For the convex resource function, a bicriteria analysis is provided, where the first (respectively, second) criteria is to minimize total weighted completion time (respectively, total resource consumption cost). The first problem is to minimize the weighted sum of the total weighted completion time and the total resource consumption cost. The second problem is to minimize the total weighted completion time subject to the total resource consumption cost is bound. These both problems are NP-hard, we propose some heuristic algorithms and a branch-and-bound algorithm to solve the problems.